冷再生機(jī)就地冷再生的施工工藝
來(lái)源:http://www.beianedu.cn/ 日期:2023-07-17
冷再生機(jī)是為適應(yīng)城鄉(xiāng)道路建設(shè)而設(shè)計(jì)制造的具有環(huán)保、高效的道路施工設(shè)備,作業(yè)時(shí)在對(duì)舊瀝青路面進(jìn)行銑刨、破碎的同時(shí),添加穩(wěn)定劑(水泥、石灰、水等),就地拌和通過(guò)整形、壓實(shí)而形成新的道路基層。下面冷再生機(jī)租賃廠家來(lái)講講冷再生機(jī)就地冷再生的施工工藝。
The cold recycling machine is an environment-friendly and efficient Roadworks equipment designed and manufactured to adapt to the construction of urban and rural roads. During operation, when milling and crushing the old asphalt pavement, it adds stabilizers (cement, lime, water, etc.), and mixes in place to form a new road base through shaping and compaction. Below, the leasing manufacturer of the cold regeneration machine will explain the construction process of on-site cold regeneration of the cold regeneration machine.
特點(diǎn):
Features:
1、采用大功率中冷增壓發(fā)動(dòng)機(jī),功率儲(chǔ)備系數(shù)高,動(dòng)力強(qiáng)勁。
1. Adopting a high-power intercooled turbocharged engine, with high power reserve coefficient and strong power.
2、液壓系統(tǒng)采用有實(shí)力的品牌液壓泵和馬達(dá)。
2. The hydraulic system adopts powerful brand hydraulic pumps and motors.
3、灑水系統(tǒng)采用液壓驅(qū)動(dòng),所需灑水量采用高精度流量調(diào)節(jié)閥控制,利用微控制器根據(jù)拌和深度
3. The watering system is hydraulically driven, and the required amount of water is controlled by a high-precision flow regulating valve. A microcontroller is used to adjust the mixing depth
4、工作速度、精準(zhǔn)控制灑水量。
4. Working speed, precise control of sprinkler volume.
5、方便的“敲入敲出”式銑拌刀頭,縮短了停機(jī)更換時(shí)間。
5. The convenient "knock in and out" type milling and mixing cutter head shortens the downtime for replacement.
就地冷再生施工工藝
On site cold regeneration construction process
1、對(duì)舊路結(jié)構(gòu)狀況進(jìn)行調(diào)查,并鋪筑試驗(yàn)路,以確定需要再生的深度和新集料的添加量等工藝參數(shù),長(zhǎng)度 不宜小于200米。
1. Conduct an investigation into the structural condition of the old road and pave a test road to determine the depth of regeneration and the amount of new aggregate added, and other process parameters. The length should not be less than 200 meters.
2、冷再生施工前應(yīng)將舊路路面清掃干凈,并將舊路明顯的沉陷、坑槽進(jìn)行填平處理。
2. Before cold recycling construction, the old road surface should be cleaned and any obvious subsidence or potholes on the old road should be filled and leveled.
3、人工或機(jī)械攤鋪添加劑(水泥、石灰、新集料等),按設(shè)計(jì)的添加量計(jì)算每平方米的添加量。
3. Artificial or mechanical paving of additives (such as cement, lime, new aggregates, etc.) shall be calculated based on the designed addition amount per square meter.
冷再生機(jī)租賃
4、冷再生機(jī)進(jìn)行作業(yè)。施工過(guò)程中,應(yīng)隨時(shí)檢查深度及速度,以保證再生深度及破碎的混合料級(jí)配合理。
4. Cold regeneration machine for operation. During the construction process, the depth and speed should be checked at any time to ensure that the regeneration depth and the gradation of the crushed mixture are reasonable.
5、使用推土機(jī)初找平,并均勻排壓,然后使用平地機(jī)刮平至設(shè)計(jì)高程。
5. The bulldozer shall be used for initial leveling, and the pressure shall be discharged evenly, and then the Grader shall be used for leveling to the design elevation.
6、檢測(cè)含水量,必要時(shí)補(bǔ)水,使其符合佳含水量,然后進(jìn)行路面碾壓形成新的道路基層。
6. Check the water content, add water if necessary to make it meet the optimal water content, and then roll the road surface to form a new road base.
7、道路基層養(yǎng)生。養(yǎng)生時(shí)間不少于7天,養(yǎng)生期間進(jìn)行交通管制。
7. Road base maintenance. The health preservation period shall not be less than 7 days, and traffic control shall be implemented during the health preservation period.
8、鋪筑面層,壓實(shí)形成新的路面。
8. Pave the surface layer and compact it to form a new road surface.
冷再生機(jī)就地冷再生的施工工藝相關(guān)內(nèi)容就講解到這里了,希望能夠給您好的幫助,更多事項(xiàng)就來(lái)我們網(wǎng)站http://www.beianedu.cn咨詢!
That's all for the construction process related to on-site cold regeneration of the cold regeneration machine. We hope it can provide you with good help. For more information, please come to our website http://www.beianedu.cn consulting service