冷再生機施工前的準備工作主要包括人員準備、機械準備、材料準備、交通協(xié)調及后勤保障。
The preparation work before the construction of the cold regenerator mainly includes personnel preparation, machinery preparation, material preparation, traffic coordination and logistics support.
(1)材料要求:水泥選用強度等級為32.5、初凝時間≥3h、終凝時間≤10h且≥6h硅酸鹽或普通硅酸鹽水泥。水泥應具有良好的工作性、低水化、高后期強度、耐久性、耐腐蝕性和抗裂性能。
(1) Material requirements: Portland or ordinary portland cement with strength grade of 32.5, initial setting time ≥ 3h, final setting time ≤ 10h and ≥ 6h shall be selected. Cement shall have good workability, low hydration, high late strength, durability, corrosion resistance and crack resistance.
(2)機械要求:工程施工過程通過再生機組來完成,再生機組包括:冷再生主機、水泥稀漿車、平地機、壓路機等。
(2) Mechanical requirements: the construction process of the project is completed by the regeneration unit, which includes: cold regeneration host, cement slurry truck, grader, roller, etc.
(3)人員要求:工程技術人員及機械操作人員應經過冷再生培訓并經過考核合格后方可上崗。
(3) Personnel requirements: Engineering and technical personnel and mechanical operators shall be trained in cold regeneration and qualified after examination.
(4)工程協(xié)調:作好施工總體計劃,采取不中斷交通半幅施工,作好施工期間交通疏導工作,準備施工作業(yè)面的遮擋。
(4) Project coordination: make the overall construction plan, take half width construction without interrupting traffic, do a good job of traffic diversion during construction, and prepare for the shelter of the construction working surface.
2、施工方案
2. Construction scheme
A、一般規(guī)定
A. General provisions
(1)對原路面的路況進行測量和調查,對高于原路面標高5cm以上的地方用銑刨機進行銑刨,并將銑刨后的舊路材料填于低于原路面標高5cm以上的坑槽。
(1) Measure and investigate the road conditions of the original road surface, use a milling machine to mill the places 5cm above the original road surface elevation, and fill the milled old road materials in the pits 5cm above the original road surface elevation.
(2)對原路進行加密挖驗,將原瀝青路面用冷再生機取樣進行標準擊實試驗,確定合適的含水量與至大干密度。
(2) The original road shall be intensively excavated and tested, and the original asphalt pavement shall be sampled with a cold recycling machine for standard compaction test to determine the appropriate water content and maximum dry density.
(3)施工過程中根據再生料含水量情況及時調整再生機設定的用水量,密切注意天氣變化,避免在雨天進行再生施工。
(3) During the construction process, adjust the water consumption set by the regenerator in time according to the water content of the recycled material, pay close attention to the weather changes, and avoid regeneration construction in rainy days.
B、試驗段施工
B. Construction of test section
工程正式開工前,選取300m的道路作為試驗路段,以確定現(xiàn)有道路的情況是否與設計要求相吻合,并在冷再生的級配、轉子的轉速及再生機械行走速度、壓實工藝幾個方面開展工作,為其余路段正式施工積累必要的數(shù)據。
Before the formal commencement of the project, 300m road is selected as the test section to determine whether the condition of the existing road is consistent with the design requirements, and work is carried out in the aspects of cold regeneration gradation, rotor speed, walking speed of regeneration machinery and compaction process, so as to accumulate necessary data for the formal construction of other sections.
(1)碾壓
(1) Rolling
當平地機對再生層找平后,采用22T振動壓路機(前進時靜壓,返回時振動)碾壓1遍,之后用自重26T振動壓路機進行碾壓2~3遍,再用膠輪壓路機終壓1遍。碾壓過程中按規(guī)范要求嚴格控制平整度。
After leveling the regenerative layer with the grader, use 22T vibratory roller (static pressure when moving forward, vibration when returning) to roll for one time, then use the self weight 26t vibratory roller to roll for two to three times, and then use the rubber tyred roller to finally roll for one time. During rolling, the flatness shall be strictly controlled according to the specification requirements.
(2)養(yǎng)生
(2) Health preservation
碾壓檢測合格后及時采用塑料薄膜覆蓋養(yǎng)生,養(yǎng)生期內中斷所有交通。因五一路比較繁忙,養(yǎng)生期為7d,養(yǎng)生期間冷再生基層表面始終保持濕潤,每天專人看管,確保再生層不因養(yǎng)生不當產生損壞。
After the rolling test is qualified, the plastic film shall be used to cover the curing in time, and all traffic shall be interrupted during the curing period. Due to the busy May 1st Road, the curing period is 7 days. During the curing period, the surface of the cold recycled base course is always wet, and special personnel are assigned to take care of it every day to ensure that the recycled layer is not damaged due to improper curing.
(3)開放交通
(3) Open traffic
冷再生機施工后,等路面強度達到要求后,用空壓機吹凈浮灰,撒布透層油后,上面灑石屑,之后開放交通。
After the construction of the cold recycling machine, after the pavement strength meets the requirements, use the air compressor to blow away the floating ash, sprinkle the prime coat oil, sprinkle the stone chips on it, and then open the traffic.
以上就是為大家介紹的有關冷再生機租賃的詳細的介紹,希望對您有所幫助.如果您有什么疑問的話,歡迎聯(lián)系我們.我們將以專業(yè)的態(tài)度,為您提供服務http://www.beianedu.cn
The above is a detailed introduction about the rental of cold regenerator, which I hope will help you. If you have any questions, please contact us. We will provide services for you with a professional attitude http://www.beianedu.cn